paint-brush-cartoon-26862976The painting of the community has begun with pressure washing being done on the perimeter wall from the west end to the Clubhouse, and on the Clubhouse itself. Paint work on those two areas will begin next week. Buildings 230, 240, 250, 260, 233, 247, 253, 267, and 273 are part of the first phase and work on concrete and stucco renovation will begin Friday the 20th and continue for up to nine weeks. Individual units in each building will be notified as work commences there. We anticipate things going smoothly and with a minimum of disruption. In some cases, cars will need to be moved and we will notify owners of those vehicles prior to work. If you have any questions or concerns feel free to contact the office.